The Smart Equipment unit is delivered with partial factory setup completed. Follow this procedure to check that the minimal settings have been performed.
- Log on to the SBH.
- From the device list screen, select the Smart Equipment unit. The RTU home page and the RTU menu structure appear.
- Navigate to .
- Set Rooftop Controller Type to VAV. If it is not set to VAV, the zone coordinator does not control as a VAV system.
- Navigate to Fan Control
Type is set to Variable
Speed. Note: In older versions of Smart Equipment firmware, Rooftop Controller Type is located in the section, and Fan Control Type is located in .
, and verify that
- Check the operation of the unit. Use the steps in the Setting the temperature control and flow parameters section to complete the configuration. Note: Ensure you have some zones blocked open to relieve duct pressure.