During start-up, the SBH300 automatically initiates a self test to verify correct operation. When you connect the supply power, the following LED lighting sequence occurs:
  • The POWER LED turns purple.
  • The FAULT LED is on solid for approximately 45 seconds and then flashes for approximately 2 minutes and 30 seconds. The FAULT LED then turns off and the RUN LED turns solid when the SBH300 is fully functional.