About this task
To copy the events from one day in the Weekly Schedule to one or more days in the same Weekly
Schedule:
Procedure
With the Weekly Schedule in Edit mode, left-click and
highlight the name of the day whose events you want to copy.
Right-click the highlighted day and select Copy from the
pop-up menu.
Left-click to highlight the name of the day (or days) where you want to copy the schedule.
Note: You can select multiple days by holding the Control or Shift key while selecting days.
Right-click the highlighted name of any target day and select
Paste from the pop-up menu. The copied schedule