Procedure
-
In the navigation bar at the top of the screen, click Response Program and select ELDR.
-
On the left of the screen, click Remove Overrides.
-
With the Start Date & Time and End Date & Time options, configure the period of
time to disable an override.
-
Enter an explanation for adding an override. This explanation appears in the Audit Log.
-
Click Save.