Use this section to understand the OBEM installation process. This table shows the order of steps that the Johnson Controls team and customer must complete from start to finish. All steps are sequential and you must follow them in the order in the table.
Step | Description | Relevant OBEM documentation |
---|---|---|
1 | Pre-visit site configuration checklists. This step is for Johnson Controls employees to assess site eligibility for OBEM. |
|
2 | Pre-visit customer checklists. This step is for customers to assess eligibility for OBEM at their site, and to provide details of the portfolio as well as IT security restrictions. |
|
3 | Data collector decision and preparation. Determine whether to use the Metasys API data collector software, or the Aaeon unit. |
|
4 | Professional Productivity Tool (PPT) preparation and configuration instructions. This step is to install and configure PPT. |
|
5 | PPT and OBEM integration. This step is to integrate PPT with the OpenBlue Enterprise Manager system. |
|
6 | OBEM configuration instructions. This step is to configure the system. |
|
7 | Post-configuration instructions (updates, enhancements, and maintenance). This step contains information about system updates and how to maintain the system. |
|