Procedure

  1. Apply power. To do this, perform one of the following options:
    • Insert the 2-position 24 V power connector plug.
    • Insert the barrel plug of the wall-mount AC adapter (FX-SC8XPS-0).
  2. Check the STAT (Status) and BEAT (Heartbeat) LEDs. When power is applied, the green STAT LED flashes. This LED indicates that the system works, with power applied. During startup, the BEAT LED may blink at 1 Hz with a 90/10 percent on/off duty cycle. When startup completes, the platform daemon starts, and the normal 1 Hz flash at 50/50 percent on/off duty cycle of the BEAT LED returns.